INF10.16 — Cooperative Network Information Exchange - Short Term ATFCM Measures services (MCDM, eHelpdesk, STAM measures)

The Cooperative Network Information will be exchanged between the systems of the operational stakeholders and the Network Manager by means of cooperative network information SWIM services, using the Yellow SWIM TI Profile, for Air Traffic Flow and Capacity Management (ATFCM) purposes.

Operational stakeholders use the NM B2B Services, which support the exchange of the following cooperative network information:

• Short term ATFCM measures (STAM)
This information exchange is supported by the following three NM B2B Services:
o The Measure Collaborative Decision Making (MCDM) Service, which supports the collaborative decision making for the implementation of a measure or individual flight actions
o The eHelpdesk Service, for requesting NMOC to apply actions to individual flights
o The Measures Service, which allows making proposals of cherry-pick regulations in support of STAM.

System requirements:

The Network Manager shall support all operational stakeholders in exchanging data electronically for cooperative network management activities, by providing the necessary SWIM services.

The access to NOP via the NM HMIs is covered by Objectives FCM11.1 and FCM11.2. This objective covers only the information exchanges between the stakeholders’ local systems and the NM system. The Network Manager system and operational stakeholder systems shall be upgraded to support the exchange of information in compliance with the EUROCONTROL SWIM Specifications, either through the Public Internet and/or NewPENS. The choice of communication service depends on a business criticality assessment from where minimum performance requirements are identified.

ANSP systems shall be upgraded to use the NM B2B Services in order to:
• Collaborate on the definition and application of STAM
AU systems shall be upgraded to use the NM B2B Services in order to:
• Collaborate on the application of STAM, when relevant

NOTE: For a full description of the services as well as of the associated system requirements, see the Family 5, in the SESAR Deployment Programme edition 2022, Approved by the European Commission.

NOTE FOR MILITARY AUTHORITIES: It is the responsibility of each military authority to review this Objective IN ITS ENTIRETY and address each of the SLoAs that the military authority considers RELEVANT for itself. This has to be done on top and above of the review of "MIL" SLoAs which identify actions EXCLUSIVE to military authorities.

Edition
2022
Stakeholders
Air Navigation Service Provider / Airspace Users / Network Manager
Type
CP1
Scope
EU
Status
Active

Context

Related Elements

Applicability Area(s) and Timescales

Applicability Area 1:
All EU SES States
(All EU SES States)
Applicability Area 2:
United Kingdom
Timescales From By Applicable to
Initial Operational Capability 01-01-2021 Applicability Area 1 + Applicability Area 2
Full Operational Capability / Target Date 31-12-2025 Applicability Area 1 + Applicability Area 2

Links to SESAR Solutions

Links to PCP ATM Sub-Functionalities

ICAO Block Modules: No associated data

References

Applicable legislation
Regulation (EU) 2021/116 on the establishment of the Common Project One
Applicable ICAO Annexes and other references
None
Deployment Programme 2022
Family 5.5.1 - Cooperative Network Information Exchange
Operating Environments

Expected Performance Benefits

Safety
-
Capacity
-
Operational efficiency
-
Cost efficiency
-
Environment
-
Security
-
  Code Title From By Related Enablers
 
ASP01 Collaborate on the definition and application of STAM
  • 01-01-2021
  • 31-12-2025
 
ASP02 Operational use
  • 01-01-2021
  • 31-12-2025
 
USE01 Collaborate on the application of STAM
  • 01-01-2021
  • 31-12-2025
 
USE02 Operational use
  • 01-01-2021
  • 31-12-2025
 
NM01 Upgrade NM systems for SWIM compliance
  • 01-01-2021
  • 31-12-2025
Code Dates
 
1999 99
2000 00
2001 01
2002 02
2003 03
2004 04
2005 05
2006 06
2007 07
2008 08
2009 09
2010 10
2011 11
2012 12
2013 13
2014 14
2015 15
2016 16
2017 17
2018 18
2019 19
2020 20
2021 21
2022 22
2023 23
2024 24
2025 25
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
INF10.16
 
20210101_20251231
ASP01
 
13%
20210101_20251231
ASP02
 
6%
20210101_20251231
USE01
 
20210101_20251231
USE02
 
20210101_20251231
NM01
 
20210101_20251231

Supporting Material

Title Related SLoAs

SDM - Standardisation and Regulation support to CP1 deployment 2021, Deliverable D1.1.1 07/2021

https://www.sesardeploymentmanager.eu/publications/deployment-programme

ASP01, ASP02, NM01, USE01, USE02

Consultation & Approval

Working Arrangement in charge
-
Outline description approved in
Latest objective review at expert level
Commitment Decision Body
-
Objective approved/endorsed in
Latest change to objective approved/endorsed in