FCM07 — Calculated Take-off Time (CTOT) to Target Times for ATFCM Purposes

Target times (TT) shall be applied to selected flights for ATFCM purposes to manage ATFCM at the point of congestion rather than only at departure. Where available, the target times of arrival (TTA) shall be derived from the Airport Operations Plan (AOP). TTAs shall be used to support airport arrival sequencing processes in the en-route phase.
NM's systems shall be able to adjust CTOTs based on refined and agreed TTAs at the destination airport; TTAs shall be integrated into the AOP for subsequent refinement of the NOP.
Flight data processing systems may need to be adapted in order to process downlinked trajectory data (ADS-C EPP).

In a first step, NM system will transmit calculated target times (TT) at the most penalising regulation reference point in addition to calculated take-off times (CTOT) to all concerned users of CTOT. Those users should be able to manage this new feature and potential system upgrades should be foreseen

NOTE: This is an "Initial" objective to provide advance notice to stakeholders. Some aspects of the objective require further validation.

NOTE FOR MILITARY AUTHORITIES: It is the responsibility of each military authority to review this Objective IN ITS ENTIRETY and address each of the SLoAs that the military authority considers RELEVANT for itself. This has to be done on top and above of the review of "MIL" SLoAs which identify actions EXCLUSIVE to military authorities.

Edition
2022
Stakeholders
Air Navigation Service Provider / Airport Operator / Airspace Users / Network Manager
Type
PCP
Scope
EU+
Status
Removed

Context

Related Elements

Applicability Area(s) and Timescales

Applicability Area:
All ECAC States except: Armenia, Azerbaijan, Türkiye, Ukraine
Timescales From By Applicable to
Initial operational capability 01-01-2017 - Applicability Area
Full operational capability - 01-01-2022 Applicability Area

Links to SESAR Solutions

Links to PCP ATM Sub-Functionalities

References

Applicable legislation
Regulation (EU) No 716/2014 on the establishment of the Pilot Common Project
Applicable ICAO Annexes and other references
None
Deployment Programme 2022
-
Operating Environments
Terminal Airspace
En-Route
Network

Expected Performance Benefits

Safety
-
Capacity
The involvement in TT generation of local actors has a positive impact on capacity and delay reduction.
Operational efficiency
Reduced flight time in TMA leading to an optimised flight arrival management in the TMA. Reduction of holdings along with radar vectoring, with positive impact on fuel burn.
Cost efficiency
-
Environment
-
Security
-
  Code Title From By Related Enablers
 
ASP01 Adapt ATM/ATFCM systems to enable the Target Times extraction and presentation to relevant operational personnel
  • 01-01-2017
  • 01-01-2022
 
ASP02 Implement procedures and processes in support of Target Time sharing
  • 01-01-2017
  • 01-01-2022
 
ASP03 Adapt systems to support Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
 
ASP04 Implement procedures and processes in support of Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
 
APO01 Adapt airport systems, as required, to support reconciled target times for ATFCM and arrival sequencing
  • 01-01-2019
  • 01-01-2022
 
APO02 Implement procedures and processes in support of Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
 
USE01 Adapt systems at airspace users' operations centers to enable Target Times extraction and distribution
  • 01-01-2017
  • 01-01-2022
 
USE02 Implement procedures and processes to adhere to TTs, to the extent possible
  • 01-01-2017
  • 01-01-2022
 
USE03 Adapt systems to support Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
 
USE04 Implement procedures and processes in support of Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
 
NM01 Adapt NM systems to support Target Time sharing
  • 01-01-2017
  • 01-01-2022
 
NM02 Adapt systems to support Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
 
NM03 Implement procedures and processes in support of Calculated Take-off Time to Target Times for ATFCM purposes
  • 01-01-2019
  • 01-01-2022
Code Dates
 
1999 99
2000 00
2001 01
2002 02
2003 03
2004 04
2005 05
2006 06
2007 07
2008 08
2009 09
2010 10
2011 11
2012 12
2013 13
2014 14
2015 15
2016 16
2017 17
2018 18
2019 19
2020 20
2021 21
2022 22
2023 23
2024 24
2025 25
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
FCM07
 
20170101_20220101
ASP01
 
20170101_20220101
ASP02
 
20170101_20220101
ASP03
 
20190101_20220101
ASP04
 
20190101_20220101
APO01
 
20190101_20220101
APO02
 
20190101_20220101
USE01
 
20170101_20220101
USE02
 
20170101_20220101
USE03
 
20190101_20220101
USE04
 
20190101_20220101
NM01
 
20170101_20220101
NM02
 
20190101_20220101
NM03
 
20190101_20220101

Supporting Material

Title Related SLoAs

EUROCONTROL - ATFCM Users Manual - Edition 20.0

https://www.eurocontrol.int/publication/atfcm-users-manual

ASP01, ASP02, NM01, USE01, USE02

Consultation & Approval

Working Arrangement in charge
NETOPS
Outline description approved in
-
Latest objective review at expert level
05/2016
Commitment Decision Body
Provisional Council (PC)
Objective approved/endorsed in
09/2016
Latest change to objective approved/endorsed in
-